24.11.2015 - The project is progressing to plan

24.11.2015 - The project is progressing to plan -

Much has changed at the site since the ceremony at the end of August to mark the start of work on the Albula Tunnel. The miners, blasters, foremen and everyone else involved have moved in, and work was proceeding at full tilt at the Preda and Spinas sites just before the winter break.

Tunnelling work started in late August, from both the Preda and Spinas ends. The section of loose rock at the Preda end has already been successfully dealt with, and blasting work since mid-October has allowed several metres of Allgäu slate to be excavated every day. Installation of the belt conveyors and gravel preparation system is almost complete. Three trains loaded with gravel and cement are already being despatched every week to the site station at the Preda end in order to keep the project supplied with raw materials and construction items. As the section of loose rock in Spinas is some 200 metres long, blasting work at this end cannot begin until next year. Current tunnelling progress (as of 24.11.2015) stands at 180 metres from the Preda end and 55 metres from the Spinas portal. Operations up to the hollow will be suspended for the three-month winter break from mid-December onwards.


The hollow
The hollow at metre 1,300 of the tunnel has been enlarged to twice its original width in order to allow closer access to the Rauwacke geological fault zone in the cellular limestone, and to optimise the additional tasks involved in the deliberate freezing of this area. The holes designed to house the freezing tubes are currently being drilled into the mountain. This work will continue throughout the winter (apart from the Christmas holidays) in three-shift days and seven-day weeks, right up to the final phase. The actual freezing of the rock can begin in April 2016.

31.08.2015 - Work begins on the reconstruction of the Albula Tunnel

31.08.2015 - Work begins on the reconstruction of the Albula Tunnel

The ceremony marking the start of work took place at the northern end of the Rhaetian Railway's Albula Tunnel in Preda on Monday 31st August 2015. After 14 months of intensive preparations, the actual tunnelling work could now begin. This was an important milestone for both the RhB and the companies engaged by it to carry out the work. A small inauguration ceremony was held in the presence of the RhB's board chairman Stefan Engler, the media and representatives and employees of the firms engaged to carry out the reconstruction work.

News

News

Drilling and excavating machines are hard at work every day on the Rhaetian Railway's biggest construction site. The first turf was officially dug in summer 2014, marking the start of installation work at both the Preda and Spinas ends of the tunnel. The actual excavation of the new Albula Tunnel began in August 2015. There was thus a gap of fourteen months, occupied by intensive preparations, between that initial starting whistle and the commencement of tunnelling work. This section contains information updates and highlights of the construction work on the new Albula Tunnel, along with a summary of the past few months' events.